Huatacondo’s solar plant and BESS in Chile remained at 0% availability 62 days after the August 27 cyberattack.
Huatacondo’s 103 MW solar plant and its 98 MW/312 MWh battery system were still disconnected and at 0% availability through October 28, 62 days after the August 27 incident, according to EnergySage Chile. The National Electric Coordinator’s daily report still linked the outage to the cyberattack on Huatacondo’s facilities.
Huatacondo’s 103 MW solar plant and its 98 MW/312 MWh battery system remained disconnected and at 0% availability through Oct. 28, 62 days after the Aug. 27 incident, according to EnergySage Chile. The National Electric Coordinator’s daily report still listed both assets as out of service and continued to cite a cyberattack on Huatacondo’s facilities as the cause.
What did the National Electric Coordinator record?
The National Electric Coordinator’s daily log kept the Huatacondo plant and its battery system disconnected, with 0% availability, and continued to attribute the outage to the cyberattack. That operating status shows that, at least through Oct. 28, the solar and storage assets had not returned to service.
The agency’s reference is significant because this was not a brief interruption or an immediate recovery. Specialized coverage cited by Energy Storage News reported on Oct. 27 that the system was still offline, with the same cause listed in the daily report. One day later, EnergySage Chile was still showing the same status for the plant and its BESS.
How broad was the outage?
The outage affected both the solar plant and the battery system, which were logged at 0% availability for more than two months. EnergySage Chile said the site includes a 103 MW plant and a 98 MW/312 MWh storage system, with no return to service through Oct. 28.
The timeline was also defined by the incident date, Aug. 27. Since then, the prolonged offline status turned the case into an issue of resilience and OT operational continuity for Chile’s power system, beyond the initial event reported as a cyberattack.
What is known and what remains unconfirmed?
Independent coverage said it had not yet been established whether the outages at Huatacondo, Santa Rita, Olivos and Espinos were connected, or what the origin of the attack was, or which systems were compromised. That point, attributed by PV Solar Fast, leaves the technical scope of the incident unresolved.
For now, the confirmed fact is that Huatacondo and its BESS remained unavailable, and the National Electric Coordinator’s records continued to attribute the event to a cyberattack. Everything else, including whether the outages were related, remained unconfirmed in the cited coverage.
What operational impact did the cyberattack have on Huatacondo?
The cyberattack kept Huatacondo’s solar plant and battery system out of service for more than two months, with 0% availability through Oct. 28. That affected both the 103 MW plant and the 98 MW/312 MWh storage system.
The National Electric Coordinator continued to log both assets as disconnected and to attribute the outage to the Aug. 27 incident. The coverage cited by EnergySage Chile and Energy Storage News showed that recovery was not immediate and that the case remained open at least through late October.
Sources
- Chile solar and battery system remain offline after cyberattackess-news.com· Energy Storage News
- La ciberseguridad de las redes eléctricas carece de reconocimiento tarifario específico en once países de América Latinapv-magazine-latam.com· pv magazine Latinoamérica
- The attack took a day; getting back on the grid has taken 62 daysenergysage.cl· EnergySage Chile
- Ciberataque deja dos meses fuera de servicio a una plantapvsolarfast.com· PV Solar Fast